Update 25.06.2021
In week 25, 2021, the fibre optic cable installations were also finished.
The construction of the 40 km fibre optic cable route is thus completed and will be available for use by our customers from 1 July 2021.
Our account management team will be happy to discuss any questions you may have. Please do not hesitate to contact us.
We would like to thank all those involved for their engagement and for the good cooperation!
Original News:
On schedule, on March 8, construction started on lot 1 of the 40 km long route from the Schenkenberg / Dauerthal gas station to Hawe Telekom and Netia on the Polish border near Pomellen. Lot 2 followed on 6.4.
Completion is scheduled for week 22/2021.